Danaos

Mine Development & Expansion

ERP Software for Mine Development and Expansion Projects

Mine development and expansion projects combine large-scale earthworks, heavy plant utilisation, infrastructure construction, and phased production ramp-up under strict safety, environmental, and cost control requirements.

ProjectVIEW ERP supports mining contractors by integrating estimating, plant and equipment cost tracking, labour productivity, materials procurement, change and variation control, and cost-to-complete forecasting into a single enterprise platform, delivering real-time commercial visibility across capital-intensive, schedule-driven mine development programs.

ProjectVIEW AI is fully available in ProjectVIEW v12. It includes the ProjectVIEW AI Assistant, the MCP connector and specialized AI agents. These agents send risk alerts and propose actions, while your team keeps approval authority.

Mine Development & Expansion

Explore specialist areas

Choose the sector that matches your operation.

  • Brownfield Expansion & Mine Upgrades

    Expansion and upgrade of existing mining operations requiring tight coordination between ongoing production, new construction works, and controlled management of scope, cost, and disruption.

  • Greenfield Mine Development

    Development of new mining sites involving large-scale earthworks, infrastructure construction, contractor mobilization, and disciplined control of capital costs from early works through commissioning.
FAQ

ERP for mine development and expansion

How do you build a cost and schedule baseline for a greenfield mine?

Break development into packages such as earthworks, haul roads, utilities and plant construction. Link the Bill of Quantities (BoQ) to work breakdown structure (WBS) activities and cost codes. Use cost recipes to estimate resource quantities, costs and productivity. For a haul road, the BoQ sets the volume to move and the WBS shows when the road must be ready for plant deliveries. Compare measured quantities and actual costs with that baseline.

How do you plan a brownfield mine expansion around ongoing production?

Agree access restrictions, outage windows and tie-in dates with operations. Schedule a conveyor tie-in during an approved outage and plan preparatory work around it. Link the expansion BoQ to its WBS activities to track scope and cost separately from routine production. If the outage moves, review the schedule for idle crews or equipment and potential commissioning delays.

How do you assess the cost and schedule impact of a mine development variation?

Compare the proposal with the approved BoQ and WBS. If revised geotechnical information requires extra excavation and ground support, add sub-items under the affected BoQ item, estimate additional labour, plant and materials, and link the revised quantities to the affected WBS activities. Link the geotechnical report, revised drawings and site records for authorized reviewers. After approval, record the revised baseline as a new version so the original remains traceable.

Search or Ask AI